Pathlaiy-Birgunj Road Project, Trade-Route Improvement Project, DoR.

Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Road
North-South Trade Route Improvement Programme Directoriate
Pathlaiya - Birgunj Road Project.
Pathlaiya, Bara.
Duration : (2075-09-09 to 2077-06-06)


.....................................................................................................................................................................................................................................................................................................................

                
......................................................................................................................................................................................................................................................................................................................
Location of Project: Bara & Parsa District.
Summary of Work: Upgradation of Two Lane road into dedicated Six Lane with separated Intermediate Service Lane. 
Fig.: Typical Cross-Section of Road Section.

Google Location of Project Site:

General Description of Work within this project office:

There are total 19 Contract within this office. Out of them 9 Contracts in Road Sector, 4 Contracts in Bridge Sector & 6 Small Contracts for Utility Relocation.
Fig: Weitage of Different Infrastucture Contract on Overall Project Work.


Road Sector: 
  • Total Contract                       =      9 No.
  • Total Contract Length           =     32 Km
  • Six-Lane Black Top Length  =    15 Km 
  • Three Lane Black Top           =    5 Km                                  
  • Non- Black Top Length         =    12 Km      
Bridge Sector : 
  • Total Bridge Contract             =   4 Nos.
  • Total No. of Bridge                 =  10  All Bridge are 2 Span Minor Bridge.
  • Superstucture Completed        =  3 No. (2 Bridge (2Span) & 2 Bridge (1 Span)
  • Sub Structure & Foundation    =  Completed.
Utility & Temple Relocation:
  • Total Temple                           =  7
  • Shifted Temple                        =  7
  • All Complete, remaining minor temples are agreed to replace by local authority .

Sectoral Distribution of Work:    ............................................................................................................

  1. Road Components: Eight Contract Package for Road Upgradation and One Package for Current Installation of Street Light & Drainage Cover in settlement area. It contribute about 82% of whole work within project office. The Contracts were expected to complete within two years although fifth year is running with progress (Financial - 58% & Physical-65%) in this Sector.
    Road Upgradation Contracts.
  2. Bridge Components: Three Contract Package for Ten Bridges Construction and One Package for Box Culvert Construction. It contribute about 18% of whole work within project office. The Contracts were expected to complete within two years although fourth year is running with progress (Financial - 58% & Physical-65%) in this Sector.
    Bridge & Box Culvert Construction.
  3. Relocation of Utilities & Temples within RoW : All Six Temples & more than 90% of the Electric Poles, Telicome, Watersupply & Sanitation work are completed.
    Temples & Utility Relocation

Annual Progress Pattern: 
Annual Progress of Each Contract.
Annual Progress Trend & Contribution.

BERUJU CLEARANCE SITUATION TILL DATE:



PROGRESS REVIEW MEETING PRESENTATION FOR FY:076-77:

Photographs of Project Works:

 

Rennovated Russian EW Highway Statue at Pathlaiya Junction.
Media Coverage:
पत्र-पत्रिकामा छापिएका केहि सम्बन्धित समाचारहरु :



    • I would hereby handover remaining project be completed by my next collogue as Project Manager by end of the month. 